Effective January 1, 2027, Updates to the Energy Code To Impact New Construction and Substantial Renovations of Buildings

The DC Department of Buildings (“DOB”) recently announced new energy code rules will take effect on January 1, 2027. Based on recent amendments to the DC Energy Code as set forth in the Fiscal Year 2027 Budget Support Act of 2026 (the “BSA”; D.C. Law 26-189; effective October 2, 2026). Specifically, Section 2111 of the BSA, the Clean Energy DC Building Code Amendment Act of 2026 (“Clean Energy Code”), amends the requirements found in D.C. Code § 6-1453.01 and impacts how the DC Energy Conservation Code (Title 12-I[CE] of the DC Municipal Regulations) applies to certain construction projects.

The Clean Energy Code amendments only apply to “commercial buildings” as that term is defined in the 2015 International Energy Conservation Code (“IECC”). From a Construction Code perspective, this means residential one and two-family dwellings, townhouses, as well as Group R-2, R-3 and R-4 buildings three stories or less in height above grade plane, are exempt. Thus, the new rules apply to any four-story apartments, dormitories, and hotels, as well as any commercial buildings.

WHO IS AFFECTED? 
Effective January 1, 2027, all privately-owned buildings applying for a building permit for either new construction or an addition greater than 10,000 square feet must have all-electric heating and hot water. 

In addition, energy conservation for the project must equal the requirements found in the 2024 IECC if either of the above two conditions apply (new construction or addition) or if the project is a “Level 3 Alteration” under the International Existing Buildings Code (“IEBC”) (e.g., an alternation worth 50% or more of the building’s value).

For all publicly owned, leased, and financed buildings and projects, the following is effective now through December 31, 2027:

RequirementsRequired for Commercial Buildings*Required for Residential Multifamily Buildings, 4 Stories or More**
Conserve energy equal to or greater than Appendix Z of DCMR, Title 12-I  Yes***  Yes
Obtains energy from renewable energy sources as required by Appendix Z  Yes***  No
Renewable energy generated on site, wherever feasible  Yes    No
No on-site fuel consumption for thermal energy, except for backup power generation (all-electric requirement)  Yes  Yes

* Excluding temporary buildings and additions less than 10,000 sf.
** Excluding new buildings and additions less than 10,000 sf.
*** Excluding police, fire, emergency response, and Office of Unified Communications facilities, and aquatics centers permit applications.

ANY OTHER RELIEF? 
If your building project is in the design phase before December 31, 2026, your project may be exempt.  You may follow the 2017 version of the DC Energy Conservation Code – Commercial provisions (DCMR, Title 12-I[CE]). See Section 123 (the transitory provisions) in DCMR, Title 12-A for the details. To qualify, you must submit as supporting documents to your building permit application a copy of the design contract for the scope of work between the design professional and the building permit applicant, showing it was signed and dated before December 31, 2026.

ANYTHING ELSE?
Development of DC’s new construction code to update the current Construction Codes Supplement of 2017 continues. The anticipated effective date for the 2027 Construction Codes is January 1, 2028, pending the District of Columbia’s completion of the rulemaking process and subsequent review by the City Council. The 2027 Construction Codes include updates to the Energy Conservation Code, as well as the Green Construction Code and it is recommended that impacted stakeholders submit comments during the rulemaking process.

Should you have any questions about this matter, please contact Lyle M. Blanchard, Esq., at lmb@gdllaw.com.